In August of this last summer we disassembled major
parts of our chairlift as it was deemed to be prudent
to rebuild them after 40 years of service. General Manager
Dennis Evinrude solicited bids from industry experts
to lead the repair team and the services of Larry Wollum
were retained. Larry was a long time field repair representative
from the firm that built our lift and is considered
one of the most knowledgeable people in the lift industry.
The
Ausblick portion of the team consisted of Snowmaking
& Groomer Manager Wes Cashwell,
his assistant Rick Bull, and myself
providing oversight of the project.
The
photos will indicate the depth to which we go to make
these repairs in order to give Ausblick the best possible
assurance of a trouble free season. In the last
forty years we have had less than forty hours of downtime
with this lift and strive to keep that number
as low as possible. Enjoy the photos and fell free to
contact me with any questions you might have.
1)
Chairlift Cable is rigged to release tension on upper bullwheel.
2) Cable has been lowered away from bullwheel in preparation
for bullwheel removal.
3) Removal of Drive Terminal bullwheel.
3a) Bullwheel is removed and ready for transport.
4) Partially removed axle assembly from Tower 1
at loading area
5) Upper Terminal minus bullwheel.
6)
Upper bullwheel arrives in maintenance building.
7) Heating shaft to facilitate removel.
8) Shaft and Lower Bearing removed.”
9)
Smoothing the shaft with emery cloth.
10) Bearing race drops into hole.
11)
Bearing race will expand as it warms, locking itself into
place.
12) Pouring liquid nitrogen into
cooler for bearing race shrinking
13) Bearing race submerged in liquid nitrogen at
over 300 degrees below zero.
14) New Tower 1 components.
15) Cutting old counterweight rope at Drive Terminal.